Downwell took possession of the site, which had been heavily fly-tipped and had a lot of overgrown vegetation, including Japanese Knotweed.

We prioritized removing and treating the Knotweed, which was growing at the side of former industrial buildings. 

Further treatment of the Knotweed commenced upon the demolition and clearance of the buildings.

The site was cleared of all vegetation and fly-tipping. Materials were separated and sent for recycling.

Upon clearance of the above-ground area, testing started to determine the contamination levels across the site.

A slurry wall was installed on the left-hand side of the site to stop contamination from the adjacent property. This area had been a former basement and required deep excavation. As part of the construction, a new basement is in this position.

Excavation of the contaminated areas of the site began after the removal of concrete slabs and underground obstructions.

Contaminated soil was removed and taken to treatment areas before reinstatement into the ground.

All groundwater went through a cleaning process before being pumped away.

 