Times House Enabling Works – Site Progress

Our Times House project in Wapping is off to a great start with site progress moving on swiftly. Following initial site setup we are now commencing with scaffold erection and various elements of internal enabling works.

Demolition is due to commence once the temporary steel supports have been erected throughout the floors of the building. Once these have been completed the building will be suitably supported to allow for the sections of facade and the concrete slabs to be removed.

We have appointed Prime Safety to complete our external safety audits. This is in addition to our own H&S audits that will be completed weekly. Prime Safety have been appointed to provide us with advice on any H&S issues we may have and to monitor our performance on site.