Downwell Enabling was appointed to deliver a major structural and civil works package for Rainham Steel, ensuring continuity of operations throughout the project. This £4.9m scheme involved the removal and replacement of critical gantry infrastructure to support long-term site functionality.
Scope
- Removal of the existing steel crane gantry structure
- Installation of new piled foundations for the replacement gantry
- Construction of a reinforced, ground-bearing floor slab with associated drainage works
- Erection of a new steel gantry frame designed for durability and performance
- Coordination of all works to align with live operational requirements
- Implementation of robust safety and access controls within active working zones
Challenges & Expertise
Maintaining full operational capability during major civil works presented significant logistical challenges, particularly given the crane’s critical role in material handling. Downwell’s delivery team applied detailed pre-construction planning and sequencing strategies to ensure compliance with client requirements while upholding the highest standards of safety and efficiency.
Outcome
The project was delivered seamlessly, allowing Rainham Steel to retain full site functionality throughout. The new gantry structure provides a modernised, robust solution ready to support future operations.