Downwell Enabling is proud to be delivering the £6.5m site-wide enabling works package for our valued client, Global Switch, at their London North Data Centre. This strategically important project is progressing well ahead of the main construction phase, ensuring the site is fully prepared for the next stage of development.
Scope
The project will create a safe, secure and operationally ready environment for the incoming main contractor. The enabling works are complex and multifaceted, particularly given the live nature of the data facility. Key elements include:
- Identification of existing services to inform safe excavation and diversion planning
- Deep drainage works, including pipe jacking, trenching and timber heading for sewer connections
- Demolition of redundant infrastructure to clear the site for new development
- Deep-level excavation within a live data centre environment, requiring precision and care
- Diversion of critical services including fibre, mains, drainage and communications
- Pile preparation, incorporating probing, platform installation and full UXO clearance
- Site-wide security upgrades, featuring CCTV, lighting, perimeter fencing and SRI-rated bi-fold gates
- Hard landscaping to support long-term site functionality and aesthetics
Challenges and Expertise
Operating within a live data centre presents unique challenges. Our teams are working in high-risk environments where continuity, safety and quality are paramount. This project exemplifies Downwell’s capability to deliver enabling works that balance technical complexity with operational sensitivity.
Outcome
The project is on track to complete on schedule, providing Global Switch with a fully prepared site that meets stringent security and operational standards. It stands as a testament to Downwell’s expertise in delivering enabling works for critical infrastructure projects.